Question
A is large property developer who is listed on the Kuala Lumpur Stock Exchange. B is a building contractor. A employed B in 2008 to build a large office complex comprising 3 towers on a piece of land in the heart of Kuala Lumpur. C is a wealthy individual who owns many pieces of property in Kuala Lumpur and Singapore. C is also a shareholder in A but is not involved in its management. The Building contract between A and B states that, "Any dispute, controversy or claim arising out of or relating to this contract, or the breach, termination or invalidity thereof, shall be decided by arbitration in accordance with the Rules for Arbitration of the Regional Centre for Arbitration Kuala Lumpur by three Arbitrators appointed in accordance with the rules.". The dispute involves the “installation of a chilled water system which serves the air-conditioning systems of all 3 buildings”. The main material used in this system are pipes which are sourced from one specialist supplier known as D. D is a company based in Singapore. C and her family are majority shareholders in D. The main dispute is in respect of the type and quality of pipes supplied by D. The payment mechanism between B and D is that “D will only be paid for supplying the pipes if B is paid by A for the installation of the pipes”. The pipes have been installed by B but A refuses to pay for the pipes because the Architect for the project says that the pipes are not in accordance with specification and are inferior. B has issued a notice of arbitration to resolve this dispute. D has an interest in the dispute as it will only be paid if an award in given in B’s favor. Advise as to whether there is any Conflict of Interest in respect of the Arbitrators based on the aforesaid facts given the following situations.
1. A has appointed Mr Green as arbitrator. Mr Green is an Architect by profession and has been appointed by Company A as architect for its projects. There are currently no projects for which Mr Green acts as architect for A. The last time Mr Green was appointed as architect for one of A’s projects was in 2008 which was fully completed in 2009.
2. Mr Green is also a close friend of Company A’s Managing Director and they meet at least once every week for dinner. Their children attend the same school together. However, as a rule, both A’s Managing Director and Mr Green do not speak of Company A’s business during their weekly dinners.
3. The senior most partner in Mr Green’s firm (in which he is a junior partner) has direct shareholding in Company D, the pipe specialist, and is also an executive director. A’s Managing Director was aware of this at the time of Mr Green’s appointment.
4. Company B has appointed Mr Brown as arbitrator. Mr Brown is an engineer by profession. Mr Brown is a minority shareholder in B but plays no part in its management. He only attends the annual general meetings of Company B and draws a small annual dividend.
5. Mr Brown is currently involved in another project (which is unrelated to this dispute) where his engineering company (in which he is currently the managing director) has been appointed as engineers for B. The project is very lucrative for Mr Brown and he hopes to gain other appointments with B for future projects.
6. Mr Brown has investments in various mutual funds in Singapore which in turn owns shares in both A and D. A and D are two of many other companies in which his funds are invested. These investments are passive investments in that Mr Brown has no control over. However, he does have knowledge of his funds’ investments in A and D through annual reports. He draws dividends every quarter from these mutual fund investments.
7. Mr Green and Mr Brown propose to appoint Ms April as the third presiding arbitrator. Ms April is a lawyer by profession and carries on an active litigation practice in a large partnership in Kuala Lumpur. Ms April is C’s granddaughter and Ms April regularly represents C in her legal matters. She is also the principal beneficiary named in C’s will.
8. Ms April’s partners also regularly acts for both A and C and both their subsidiaries in respect of their corporate deals. Ms April does not involve herself in these corporate matters and has no direct knowledge in the deals. However, as a partner of the firm, she derives income from fees earned from these corporate matters.
9. Another partner in Ms April’s firm is an arbitrator in another unrelated dispute involving a company which is part owned by Company B.
10. Both A and C have approached Ms April on separate occasions before, seeking to appoint her as sole arbitrator on another dispute which is not related to this dispute. She declined the request on both occasions.
When answering the above, explain the grounds and the process by which an arbitrator may be removed under the Arbitration Act, 2005. Make reference to relevant cases and guidelines. (ie: IBA Guidelines; Green List, Red List, Orange List)
Summary
The question belongs to Law, particularly dealing with business law. The question is about a dispute between parties of interest in a building which include the contractor, the contracted and a third party material contractor. A dispute regarding the quality of the material used in the installation leads to arbitration.
Total Word Count 2190
Operations management was my minor during my MBA but I faced much challenges with the problems and assignments. So once when I was stuck with my supply chain management assignment my friend Joan told me about this website. The feedback I got from them was very positive and the assignment was also very well done. All the calculations and the charts were displayed in proper manner and from then onwards I constantly took help from them.
Automata were definitely my problem area as far as computer science and programming assignments are concerned. However, after consulting the experts here everything was sorted out and my grades also improved. I will definitely thank the wonderful team of HwA to help me out during my crunch time.
I would like to thank TheReliableTutor.com and its team for the wonderful service. You guys have produced what I exactly asked for and were so efficient with deadlines. I would definitely recommend this service.
I was unable to find any sort of solution to my case study related to the hip and femur fracture patient. However, I was surprised to see that in HwA they have a separate group of nursing experts for the musculo-skeletal assignments and homeworks. It was really helpful and till now I keep in touch with HwA for all my nursing solutions.
The tutors at TheReliableTutor.com are experts at taxation laws of multiple countries which makes their research work of very high quality. I am very impressed with the quality of taxation assignment tutoring I received for my assignment help request on capital transfer tax. The tutor assigned to me was aware of all the latest judicial amendments and litigation which made the assignment content that much better. I got a B and now have taken a package for the entire semester.
Comments
this is a very good website
I have 50 questions for the same test your page is showing only 28
hi can you please help or guide me to answer my assignments. thanks
hi can anyone help or guide me to my assignments. thanks
This solution is perfect ...thanks
Hello Allison,I love the 2nd image that you did! I also, had never heard of SumoPaint, is something that I will have to exolpre a bit! I understand completely the 52 (or so) youtube videos that you probably watched. Sometimes they have what you want, sometimes they don't! However, it is always satisfying when you are able to produce something that you have taught yourself. Great job!Debra 0 likes
Perfect bank of solution.
great !
thanks for the quick response. the solution looks good. :)
thnx for the answer. it was perfect. just the way i wanted it.
works fine.