Tom’s Manufacturing Company Ltd makes sophisticated custom parts on a job order basis. The company has two direct product cost categories: direct materials and direct labor. In the past, indirect manufacturing costs were allocated to products using a single indirect cost pool, allocated based on direct labor hours. The indirect cost rate was $ 230 per direct labor hour. The Manager (Mr. Bright) decided to switch from a manual system to software programs that release materials and signal machines when to begin working. Naturally thought was given to whether the existing costing would be suitable. After investigation, it was decided to adopt an activity based costing system. The manufacturing process has been organized into six activities, each with its own supervisor who is responsible for controlling costs. The following list indicates the activities, cost drivers and cost allocation rates.
|
Activity |
Cost Driver |
Cost per unit of cost driver |
|
Materials handling |
Number of parts |
$0.80 |
|
Milling |
Machine hours |
40.00 |
|
Grinding |
Number of parts |
1.60 |
|
Assembly |
Hours spent in assembly |
10.00 |
|
Inspection |
Number of units produced |
50.00 |
|
Shipping |
Number of orders shipped |
3,000.00 |
The company’s information system automatically collects the necessary data for these activities. The data for the first four jobs were as follows:
|
|
Job81 |
Job82 |
Job83 |
Job84 |
|
Direct materials cost |
$19,400 |
$119,800 |
$9,700 |
$59,900 |
|
Direct labor cost |
$1,500 |
$22,500 |
$750 |
$11,250 |
|
Number of direct labor hours |
50 |
750 |
25 |
375 |
|
Number of parts |
1,000 |
4,000 |
500 |
2,000 |
|
Number of machine hours |
300 |
2,100 |
150 |
1,050 |
|
Number of job orders shipped |
2 |
2 |
1 |
1 |
|
Number of units |
20 |
400 |
10 |
200 |
|
Number of hours in assembly |
4 |
60 |
2 |
30 |
Required:
(a) Under the conventional system previously used, calculate the manufacturing cost per unit for job orders 81, 82, 83 and 84.
(b) Under the new ABC system, calculate the manufacturing cost per unit for the four jobs.
(c) Compare the cost per unit for the four job orders calculated under both methods. Explain why the cost per unit under the conventional costing system is different from cost per unit under the ABC system.
(d) Explain why the choice of cost drivers is critical in an ABC system.
(e) Identify and explain to Mr Bright the possible advantages and disadvantages of adopting the
ABC system.
Summary
The question belongs to Accounting and it discusses about preparing a job order for a manufacturing unit. The calculations have been provided in the solution in detail.
Total Word Count NA
Download Full SolutionThe object oriented programming languages like C++ and Java were a nightmare for me and my professor rushed off with her lectures so fast that I couldn’t catch up with the syllabus. Then once HwA started helped me out with my programming homework I got more time to understand how the things summed up.
Most of my classmates where very relaxed when it was time to deliver our Research Proposal. They don’t perceive it to be important to invest time in selecting the topic. The Research Proposal writer at HwA helped me to understand the importance of choosing simpler and doable topics rather than creating challenges later during the time of conducting the research. Needless to say that I was the only one in the class to get A+ in the Research Proposal and A in the actual Research Paper.
All the curves used to confuse me a lot. I was not getting any direction while all of my classmates were cruising through their Monopoly, Oligopoly market equilibrium assignments. Then my friend Judith introduced me to HwA and then I felt much better after taking their economics homework help. They helped me understand and also get good marks.
I was stuck with my nursing case study and my friend refereed me the thereliabletutor.com website. Its been 2 yrs I have been associated with this team and they have never disappointed me. love u guys!!!
Marketing was always my area of preference. So I was confident when I got through the MBA program at Duke. But writing all the assignments over the existing work load was proving to be too much for me. The online marketing assignment expert at TheReliableTutor saved my time and effort by conducting all the research and guiding me through the material.
Comments
this is a very good website
I have 50 questions for the same test your page is showing only 28
hi can you please help or guide me to answer my assignments. thanks
hi can anyone help or guide me to my assignments. thanks
This solution is perfect ...thanks
Hello Allison,I love the 2nd image that you did! I also, had never heard of SumoPaint, is something that I will have to exolpre a bit! I understand completely the 52 (or so) youtube videos that you probably watched. Sometimes they have what you want, sometimes they don't! However, it is always satisfying when you are able to produce something that you have taught yourself. Great job!Debra 0 likes
Perfect bank of solution.
great !
thanks for the quick response. the solution looks good. :)
thnx for the answer. it was perfect. just the way i wanted it.
works fine.