Question
Using the table below, which activity is on the critical path?
|
Time (weeks) |
||||
|
Activity |
Immediate Predecessor(s) |
Most Optimistic |
Most Likely |
Most Pessimistic |
|
A |
--- |
2 |
4 |
6 |
|
B |
--- |
1 |
4 |
7 |
|
C |
A |
2 |
2 |
2 |
|
D |
B |
1 |
7 |
10 |
|
E |
D |
2 |
4 |
6 |
|
F |
E |
1 |
2 |
3 |
|
G |
C |
3 |
4 |
17 |
|
H |
D,G |
3 |
7 |
11 |
|
I |
D |
8 |
9 |
10 |
|
J |
F,H |
4 |
5 |
6 |
|
K |
I |
1 |
1 |
1 |
Summary
The short answer question belongs to Operations Management and it is about finding the activity which is on the critical path from the given activities and their respective times.
Total Word Count NA
After completing my graduation in accountancy I decided to pursue a course in taxation. However, my boat started to rock as an when I was faced with the complexity of the assumptions and considerations which needs to be made whilst calculating a business tax. I was clueless and I was looking for means to make things steady. It was then that my senior in the university suggested that I should take help from HwA and I did. The result was magnificent and while reading out their reports and calculations in my own free time, I also learned a lot.
Most of my classmates where very relaxed when it was time to deliver our Research Proposal. They don’t perceive it to be important to invest time in selecting the topic. The Research Proposal writer at HwA helped me to understand the importance of choosing simpler and doable topics rather than creating challenges later during the time of conducting the research. Needless to say that I was the only one in the class to get A+ in the Research Proposal and A in the actual Research Paper.
The topic I had selected for my dissertation required to include a report on the local markets of New South Wales. It was difficult getting help online as the data available are mostly generic and difficult to understand cohesively. Moreover, the majority of the online dissertation writing services online are located abroad somewhere in USA or UK. I was happy to see that HwA has dissertation writing helpers from not only Australia, but New South Wales itself and they cater specifically to students like us, who are from or studying in Australia.
Thank you guys for your great assistance. Loved the way you dealt with the assignment. Very satisfied with the work and will use your service again.
My main concern was having the relevant research and reference work required to be included in writing the process capability assignment solutions. The professors are very particular about referenced and researched assignments and with the process capability online experts at TheReliableTutor I have never have had to worry about that. I have received only the very best researched and 100% original process capability assignment essay from HwA.
Comments
this is a very good website
I have 50 questions for the same test your page is showing only 28
hi can you please help or guide me to answer my assignments. thanks
hi can anyone help or guide me to my assignments. thanks
This solution is perfect ...thanks
Hello Allison,I love the 2nd image that you did! I also, had never heard of SumoPaint, is something that I will have to exolpre a bit! I understand completely the 52 (or so) youtube videos that you probably watched. Sometimes they have what you want, sometimes they don't! However, it is always satisfying when you are able to produce something that you have taught yourself. Great job!Debra 0 likes
Perfect bank of solution.
great !
thanks for the quick response. the solution looks good. :)
thnx for the answer. it was perfect. just the way i wanted it.
works fine.