Question
Consider the project-related information below.
|
Activity |
Preceding Activities |
Time (Weeks) |
Crash Time |
Crash Cost per week |
|
A |
– |
3 |
2 |
$7000 |
|
B |
A |
4 |
2 |
$5000 |
|
C |
A, B |
2 |
1 |
$6000 |
|
D |
A |
3 |
2 |
$4000 |
Which one of the following options is the appropriate course of action to take if you want to reduce the project time by two weeks?
A. Crash A for two weeks because it is the only activity that reduces the time on both critical paths.
B. Crash D for two weeks because you should always crash the least costly alternative first.
C. Crash D for one week and B for one week because you should always crash the least costly alternative on each critical path first.
D. Crash B for two weeks because it is the least costly alternative on the critical path.
Summary
This multiple choice question belongs to Operations Management and it discusses about the appropriate critical path to take which can reduce the project time by two weeks.
Total Word Count NA
I had to choose my own research topic for my final year dissertation during my post graduate management course and I was really confused. I was not sure from where I can get a standard response matching the requirements of my New Zealand based university. I must admit that I was lucky to come across HwA as they have experts located in New Zealand who helped me with the assignment and more importantly helped me achieve grades, beyond expectation.
Was partying late night and forgot about my biotechnology assignment which was about to submit in 5 hours. Then approached several service providers but they refused to take up the assignment. Finally TheReliableTutor.com saved me. Submitted the assignment on time..!!!
I started taking their help while pursuing my managerial economics course in New York. So far it is a wonderful experience as unlike most of the online tutoring services, the econ tutors at HwA has industry experience and that enhances the quality of the economics papers.
Marketing was always my area of preference. So I was confident when I got through the MBA program at Duke. But writing all the assignments over the existing work load was proving to be too much for me. The online marketing assignment expert at TheReliableTutor saved my time and effort by conducting all the research and guiding me through the material.
1. In-depth research, logical and methodical progression of writing and structured context makes each and every writing assignment help that I have received from the online writing tutors at TheReliableTutor.com truly a masterpiece. My grades have improved and I am much more confident of myself now.
Comments
this is a very good website
I have 50 questions for the same test your page is showing only 28
hi can you please help or guide me to answer my assignments. thanks
hi can anyone help or guide me to my assignments. thanks
This solution is perfect ...thanks
Hello Allison,I love the 2nd image that you did! I also, had never heard of SumoPaint, is something that I will have to exolpre a bit! I understand completely the 52 (or so) youtube videos that you probably watched. Sometimes they have what you want, sometimes they don't! However, it is always satisfying when you are able to produce something that you have taught yourself. Great job!Debra 0 likes
Perfect bank of solution.
great !
thanks for the quick response. the solution looks good. :)
thnx for the answer. it was perfect. just the way i wanted it.
works fine.