Question
Below is a table of activities required to finish a project:
|
Time estimate in days |
|||
|
Activity |
Optimistic |
Most Likely |
Pessimistic |
|
1 |
19 |
20 |
26 |
|
2 |
4 |
5 |
6 |
|
3 |
6 |
6 |
6 |
|
4 |
3 |
9 |
10 |
In calculating activity times for the project, which one of the following statements is correct?
A. Activity 1 will have the lowest variance
B. Activity 2 will have a variance of 0.11
C. Activity 3 will have the highest variance
D. Activity 4 will have a variance of 0.361
Summary
This multiple choice question belongs to Operations Management and it discusses about the activities and their variance in time estimate.
Total Word Count NA
I actually had a research topic in mind but was unsure of how to frame the research question. The research question assignment expert of HwA has helped me to narrow down the topic to one single question which became the foundation of my entire research. They also helped me with the actual research paper where I got excellent grades.
This is my third time working with TheReliableTutor.com and still they amaze me every time. If anyone wants finest quality papers for assignment, then I definitely recommend TheReliableTutor.com for that.
I am very happy with the timely delivery, value for money and 24x7 availability of the online assignment experts. The tutors assigned really listened to my requirements and delivered the assignment help to my exact specifications. Thank you so much TheReliableTutor
I had no clue about my Galvanic Cell assignment till I chatted with one of the chemistry experts of HwA. The expert made the concepts crystal clear to me and helped me with the assignment. I got good grades and recommended this site to my friend.
I hugely owe to HwA for clearing my concepts as far as accounting entries are concerned. Previously I was not sure in which side of the balance sheet I need to put things like “labour overheadâ€, “capital investmentâ€, etc. But now, thanks to HwA, everything is crystal clear.
Comments
this is a very good website
I have 50 questions for the same test your page is showing only 28
hi can you please help or guide me to answer my assignments. thanks
hi can anyone help or guide me to my assignments. thanks
This solution is perfect ...thanks
Hello Allison,I love the 2nd image that you did! I also, had never heard of SumoPaint, is something that I will have to exolpre a bit! I understand completely the 52 (or so) youtube videos that you probably watched. Sometimes they have what you want, sometimes they don't! However, it is always satisfying when you are able to produce something that you have taught yourself. Great job!Debra 0 likes
Perfect bank of solution.
great !
thanks for the quick response. the solution looks good. :)
thnx for the answer. it was perfect. just the way i wanted it.
works fine.