Preparing From-To-Matrix And Determining Space Requirements
$14.00$7.001747 reads
Question
Arrange five departments in a factory to minimize the material handling costs. Each department is 20 × 20 feet and the building is 100 feet long and 200 feet wide.
- Construct a “from-to matrix”
- Determine the space requirements
- Develop an initial schematic diagram
- Determine the cost of this layout
- Try to improve the layout
- Prepare a detailed plan
The following table shows the load transported between each of the five departments
|
LOAD SUMMARY CHART |
|||||
|
DEPARTMENT |
|||||
|
DEPT |
1 |
2 |
3 |
4 |
5 |
|
1 |
|
100 |
50 |
|
|
|
2 |
|
|
200 |
50 |
|
|
3 |
60 |
|
|
40 |
50 |
|
4 |
|
100 |
|
|
|
|
5 |
|
50 |
|
60 |
|
Summary
The question belongs to Mathematics and it discusses about preparing From-To-Matrix and determining space requirements and developing initial schematic diagram.
Total Word Count 146
Related Solutions
Recently Uploaded Solutions
Write an Essay on the Importance of Public RelationsWrite an essay on the positive impact of shareholder power on bonWrite An Essay On What You Want From Work And How To Achieve ItWrite an essay/report on Marketing Mix OrientationWrite an interview structure about poultry litter convert to bio Write Article Reflection On The Article “Improving Teaching And