Compute Throughput Time and Delivery Cycle Time of a Company

$7.00$3.001210 reads

Question

During the most recent month at Coggan Corporation, queue time was 5.3 days, inspection time was 0.5 days, process time was 1.9 days, wait time was 4.5 days and move time was 0.5 days.

Required:

Compute the following:

  1. Throughput time
  2. Manufacturing cycle efficiency (MCE)
  3. Percentage of production time spent on non-value-added activities
  4. Delivery cycle time

 

Summary: This question belongs to management accounting and discusses about a company’s services and to determine throughput time, manufacturing cycle efficiency (MCE) and delivery cycle time.